The Aurora Satellite Office conducted a Pre-Construction Meeting with the Irrigators Association and Local Government Unit for Igang-Maligaya CIP Phase 2 under GAA 2022 located in Dilasag, Aurora. #TuloyAngDaloyNIA

 

Site inspection by IMO Manager Engr. Jaime A. Mananghaya, Acting Engineering Section Chief Engr. Arvin Maynard Musni and Zambales Satellite Office Head Engr. Alexius S. Academia on the ongoing construction of Zambales Satellite Office in Botolan, Zambales. #TuloyAngDaloyNIA

 

As one of the stakeholders, the Bataan Satellite Office headed by Engr. Wendell C. Martin participated in the Municipal flag raising ceremony of Dinalupihan, Bataan for the 124th Philippine Independence Day. #TuloyAngDaloyNIA

The Zambales Satellite Office conducted a courtesy call to the Brgy. Chairman of Simminublan, San Narciso, Zambales.  After the courtesy call, the staff conducted area validation and social investigation in order to start the IA Organization. #TuloyAngDaloyNIA

As of May 30, 2022, the Rehabilitation/Improvement of Various Canal Systems of AMRIS (Lateral E) located in Baliuag, Bulacan is at 54.15% accomplishment. #TuloyAngDaloyNIA

 

Surveying activities and site inspection was conducted for the Bayabas Irrigation Project located at DRT, Bulacan to verify and check the elevation of the ongoing construction of the access road. As of May 30, 2022 it is at 83% accomplishment. #TuloyAngDaloyNIA

The BANE IMO Engineering Section conducted their regular site inspection of the on-going project at Lat. C-12, Lat. D-1-C and Lat. D-0 located at Baliuag, Bulacan. As of May 30, 2022, project accomplishment for the AMRIS - Improvement of Lat. C-1 Extra/ Lat. C-12/ Lat. D/ Lat. D-1-C/ Lat. D-0/ Asana Creek is at 22.40%. #TuloyAngDaloyNIA

 

The TARZAM IMO Real Property Committee requested for a dialogue with the Legal Officer of NIA Region III to seek legal advice regarding the property at Brgy. Carangian, Tarlac City. #TuloyAngDaloyNIA

 

The Aurora Satellite Office conducted a Pre-Construction meeting with the Irrigators Association and Local Government Unit for the project Disolon CIP Phase 2 under GAA 2022 located in Casiguran, Aurora. #TuloyAngDaloyNIA

The Aurora Satellite Office conducted a Pre-Construction Meeting with the Irrigators Association and Local Government Unit for the Banco-Ramada CIP under GAA 2022 located in Ma. Aurora, Aurora. #TuloyAngDaloyNIA